Construction hinges on the results of a re-evaluation of the section from milepost 34 to 42 of the Glenn Highway Parks MP35 to MP 109 Environmental Assessment.

Below is a tentative schedule of key project events.

Project Schedule

PROJECT SCHEDULE TEXT ONLY:
Environmental Document Re-Evaluation —July 2008 to May 2011
Project Design — June 2011 to December 2014
Right of Way Acquisition — June 2012 to November 2014
Construction Begins — June 2015 (dependent upon future funding)


www.brooks-alaska.com/glennhighway / August 2008