Schedule



Project Schedule

 

Design  - Q2 2014 through Q3 2018
Traffic Analysis – Q4 2014 through Q4 2015
Noise Study – Q2 2017 through Q3 2017
Utility Relocation Agreements – Q3 2017 through Q3 2018
Right of Way – Q2 2018 through Q1 2019
Plans and Specifications for Bidding – Q3 2018
Anticipated Construction* – Q3 2019 through Q3 2021

* The start of construction is dependent on many factors including the acquisition of right-of-way and the availability of funding.